Week 1: January 20-26
- 1 hour meeting in class to finalize group members and discuss project ideas
Week 2: January 27 - February 2
- 30 minute group meeting with Ethan and Professor Fehr to discuss specifics of the project
- Discussed completing Night Light and Amazon Web Service Projects
- Planned meeting for the 30th to decide the mechanical portion of the project
- Added the red light to the design of the project, got rid of the locking aspect
- 30 minute group meeting on 1/30 to determine final hardware of project
- 1.5 hours setting up Gantt chart and budget
- 30 minute group meeting to finalize wiki project proposal