Pi Car Discovery/Logs
Revision as of 18:52, 21 September 2018 by Mayinghanjames (talk | contribs) (→Week 3 (Sept.17th ~ Sept.21st))
Week 1 (Sept.3rd ~ Sept.7th)
- Brainstormed on possible project ideas.
- Scheduled a meeting with Professor.
- Decided the best strategies about this project.
- Aimed at doing Pi Car as our projects.
Week 2 (Sept.10th ~ Sept.14th )
- James and George finished the Night Light project on the breadboard and made it work. (3hrs)
- James and George created team weekly logs and project page. (1hrs)
- Zimon found the purchase link to the puttie car.
- Discussed plan for week 3 with Dr. Feher and TA David. (0.5hrs)
Videos of Night Light on the breadboard:
Picture of Night Light Parts:
- Plan for next week: Finish Night Light Project; Update log and project page; Finalize proposal and Gantt chart; Purchase materials for Pi Car.
Week 3 (Sept.17th ~ Sept.21st)
Monday:
- James learned how to use wiki and update what we have done on the wiki, project page. (2hrs)
- George and James finished the inside part of the Night Light design. (1hrs)
- George wrote project proposal; Zimon and James reviewed (1hrs)
- Zimon designed the Gantt Chart. (1hr)
- Zimon designed the Night Light shell. (3hrs)
Tuesday:
- Zimon fixed the "Night Light" shell and hand the STL file to TA.
- James created the "Night Light" parts picture
Thursday:
- James fixed project proposal
- George created the budget chart
- Zimon created the Gantt chart
- James and George created the powerpoint for the presentation
- Zimon communicated with Dr. Feher by email
Next Week:
- Learn to use SSH
- Learn the operation of Pi Car
- Let Pi operate by using Python
- Use open CV on Pi Car
- Learn to use PIPE (Python package)