Week of 2/8
- Chose name for Project
- Completed Project Proposal
- Identified essential components of product and incorporated these components into the budget
- Finalized Gantt Chart
- Created Wiki Page for Project
Week of 2/15
- Researched prices of items on budget
- Updated Gantt Chart
Week of 2/22
- Researched OpenCV
- Updated Project Wiki
- Updated Project Budget
Week of 2/29
- Researched possible libraries to use for color point detection in images in OpenCV (imgproc)
- Downloaded OpenCV onto Flash Drive
- Loaded OpenCV onto Raspberry Pi
- Configured OpenCV to be accessible to Python programs on Raspberry Pi
Week of 3/7