Difference between revisions of "Swim Sheets Log"
Line 6: | Line 6: | ||
We met with our TA Amelia to discuss our project ideas and finalize our project proposal. | We met with our TA Amelia to discuss our project ideas and finalize our project proposal. | ||
− | We worked on our initial project proposal | + | We worked on our initial project proposal and developed our gantt chart to prepare for the semester. We considered the steps of creating an iPhone app and discussed the possible ways to approach the project. |
+ | |||
+ | We worked on research for the project goals. Hailey researched how to create a database and found bluehost as a possible webpage host for our database. This has a cost of $3.95 that would need to be budgeted for. Bluehost would allow us to link our database to the app that we will code because it is a mySQL database. | ||
+ | |||
+ | Nish and Rebecca researched... | ||
+ | |||
+ | ==Week of September 15==<br /> | ||
+ | |||
[[Category:Logs]] | [[Category:Logs]] | ||
[[Category:Fall 2017 Logs]] | [[Category:Fall 2017 Logs]] |
Revision as of 19:10, 14 September 2017
Weekly log for Swim Sheets project
Hailey Jenkins, Rebecca Bruce, Nish Chakraburt
==Week of September 8==
We met with our TA Amelia to discuss our project ideas and finalize our project proposal.
We worked on our initial project proposal and developed our gantt chart to prepare for the semester. We considered the steps of creating an iPhone app and discussed the possible ways to approach the project.
We worked on research for the project goals. Hailey researched how to create a database and found bluehost as a possible webpage host for our database. This has a cost of $3.95 that would need to be budgeted for. Bluehost would allow us to link our database to the app that we will code because it is a mySQL database.
Nish and Rebecca researched...
==Week of September 15==