Difference between revisions of "Smarter Door Log"
Jump to navigation
Jump to search
Jostrek123 (talk | contribs) |
|||
Line 15: | Line 15: | ||
*30 minute group meeting to finalize wiki project proposal | *30 minute group meeting to finalize wiki project proposal | ||
* 2 hours work on Blackjack, stuck on setting up respository structure (Johnny) | * 2 hours work on Blackjack, stuck on setting up respository structure (Johnny) | ||
+ | *2 hours building night light circuit and attempting to set up raspberry pi, got stuck on interring username and password into raspian | ||
* Goals for next week: Finish Night Light, Set up Raspberry Pi, Work on Blackjack | * Goals for next week: Finish Night Light, Set up Raspberry Pi, Work on Blackjack | ||
Revision as of 20:54, 3 February 2019
Link to Project page
Week 1: January 20-26
- 1 hour meeting in class to finalize group members and discuss project ideas
Week 2: January 27 - February 2
- 30 minute group meeting with Ethan and Professor Fehr to discuss specifics of the project
- Discussed completing Night Light and Amazon Web Service Projects
- Planned meeting for the 30th to decide the mechanical portion of the project
- Added the red light to the design of the project, got rid of the locking aspect
- 30 minute group meeting on 1/30 to determine final hardware of project
- 1 hr starting blackjack and downloading software (Katie)
- 1.5 hours setting up Gantt chart and budget
- 30 minute group meeting to finalize wiki project proposal
- 2 hours work on Blackjack, stuck on setting up respository structure (Johnny)
- 2 hours building night light circuit and attempting to set up raspberry pi, got stuck on interring username and password into raspian
- Goals for next week: Finish Night Light, Set up Raspberry Pi, Work on Blackjack