* George wrote project proposal; Zimon and James reviewed (1hrs)
 
* George wrote project proposal; Zimon and James reviewed (1hrs)
 
* Zimon designed the Gantt Chart. (1hr)
 
* Zimon designed the Gantt Chart. (1hr)
* Zimon designed the '''Night Light''' shell. (3hrs)
+
* Zimon designed the '''Night Light''' shell. (3hrs)  
 +
 
 +
Tuesday:
 +
* Zimon fixed the "Night Light" shell and hand the STL file to TA.
 +
 
 +
Thursday:
 +
* James fixed project proposal
 +
* George created the budget chart
 +
* Zimon created the Gantt chart
 +
* James and George created the powerpoint for the presentation
 +
* Zimon communicated with Dr. Feher by email
  
 
Next Week:  
 
Next Week:  
 
* Learn the operation of Pi Car
 
* Learn the operation of Pi Car
 +
* Let Pi operate by using Python
 
* Use open CV on Pi Car
 
* Use open CV on Pi Car
 
* Learn to use PIPE (Python package)
 
* Learn to use PIPE (Python package)

Revision as of 18:50, 21 September 2018

[Project Page Link]

Week 1 (Sept.3rd ~ Sept.7th)

  • Brainstormed on possible project ideas.
  • Scheduled a meeting with Professor.
  • Decided the best strategies about this project.
  • Aimed at doing Pi Car as our projects.

Week 2 (Sept.10th ~ Sept.14th )

  • James and George finished the Night Light project on the breadboard and made it work. (3hrs)
  • James and George created team weekly logs and project page. (1hrs)
  • Zimon found the purchase link to the puttie car.
  • Discussed plan for week 3 with Dr. Feher and TA David. (0.5hrs)

Videos of Night Light on the breadboard:










Picture of Night Light Parts:

Night Light Picture.jpeg











  • Plan for next week: Finish Night Light Project; Update log and project page; Finalize proposal and Gantt chart; Purchase materials for Pi Car.

Week 3 (Sept.17th ~ Sept.21st)

Monday:

  • James learned how to use wiki and update what we have done on the wiki, project page. (2hrs)
  • George and James finished the inside part of the Night Light design. (1hrs)
  • George wrote project proposal; Zimon and James reviewed (1hrs)
  • Zimon designed the Gantt Chart. (1hr)
  • Zimon designed the Night Light shell. (3hrs)

Tuesday:

  • Zimon fixed the "Night Light" shell and hand the STL file to TA.

Thursday:

  • James fixed project proposal
  • George created the budget chart
  • Zimon created the Gantt chart
  • James and George created the powerpoint for the presentation
  • Zimon communicated with Dr. Feher by email

Next Week:

  • Learn the operation of Pi Car
  • Let Pi operate by using Python
  • Use open CV on Pi Car
  • Learn to use PIPE (Python package)