Difference between revisions of "Smart Lock Log"

From ESE205 Wiki
Jump to navigation Jump to search
Line 40: Line 40:
 
*Determined a more detailed plan/outline of project (See main project page)
 
*Determined a more detailed plan/outline of project (See main project page)
 
   
 
   
 
 
==Week 3: (2/12-2/18)==
 
==Week 3: (2/12-2/18)==
-February 13, 2018 (Kelvin Xie, 30 minutes)
+
-February 13, 2018: (Kelvin Xie, 30 minutes)
 
*Finalized and uploaded Gantt chart to main project page
 
*Finalized and uploaded Gantt chart to main project page
 
*Addressed ethical issues (See main project page)
 
*Addressed ethical issues (See main project page)

Revision as of 21:53, 13 February 2018

Main Project Page

Week 0: (1/22-1/28)

-January 30, 2018: (Ahmed Hassan, 30 min)

  • Sketched General Product Prototype
  • Specified details on product's construction

Week 1: (1/29-2/4)

-January 30, 2018: (Kelvin Xie, 35 min)

  • Created project wiki and log
  • Entered preliminary project plan

-January 31, 2018: (Group, 1 hour)

  • Created basic project outline:
    • Components:
      • Hardware
        • dead bolt mount
        • Unlock mechanism
        • Microcontroller
        • Estimote beacon
      • AWS Server
        • AWS instance
        • HTTPS
        • Token authentication system
        • Unlock poll/request
      • App
        • Estimote API
        • Server request
        • Token handling
  • Determined delegation of work:
    • Each member will be the the lead of one of the above three categories. However, every member will contribute towards all three aspects of the project.
    • As it stands now, the leads for each role. are the following:
      • Hardware: Kelvin Xie
      • AWS Server: Ahmed Hassan
      • App: Graham Webb

Week 2: (2/5-2/11)

-February 6, 2018 (Group, 1 hour)

  • Created Gantt Chart
  • Determined a more detailed plan/outline of project (See main project page)

Week 3: (2/12-2/18)

-February 13, 2018: (Kelvin Xie, 30 minutes)

  • Finalized and uploaded Gantt chart to main project page
  • Addressed ethical issues (See main project page)
  • Added list of key features (See main project page)