BusyBear log

From ESE205 Wiki
Jump to navigation Jump to search

BusyBear Log

Link to Project Page

[View Project Page]

Week of 1/28/19 (1)

- 01/28

-01/29

-01/30

  • Whole Group: Met to try and finalize general goals and project. We worked on our project proposal on our Wiki page. - 2 hours

-01/31

  • Allison: Finished up the project proposal by inserting the Gantt Chart into the Wiki page. - 30 minutes

-02/1

  • Thomas and Tom: Worked on the nightlight and established a successful prototype. - 30 minutes

Goals for Next Week:

  1. Demonstrate the Night Light
  2. Start working on setting up an environment for the Pi
  3. Investigate networking and image collection for the Pi

Week of 02/04/19 (2)

- 02/04

  • Whole Group: Had meeting with Professor Feher and TA David to discuss current progress and future goals. Determined that the goals for next week will be to:
  1. Get Pi going and ready for project
  2. Complete Blackjack website
  3. Complete any tutorials for Pi
  4. Download Stretch and use Etcher
  5. Find a file for 3D printing a Pi + Camera case
  6. Research networking
  7. Consider other locations to test

- 45 minutes

-02/05

  • Tom and Allison: Downloaded Python, set up an Amazon Web Services account, and began the Blackjack tutorial. - 1 1/2 hours

-02/06

  • Allison: Finished setting up the MySQL workbench by connecting to the Amazon Web Services account. - 30 minutes
  • Whole Group: Continued working on the Blackjack tutorial and began working on the SSHing the Raspberry Pi Tutorial. Found a 3D printing design file for a Raspberry Pi Case with Camera Mount: https://www.thingiverse.com/thing:1411080 - 2 hours

[Category:Logs]]