+ | This week we researched methods of implementing are idea as well as coming up with a first draft of our design. Our design uses a solenoid valve to dispense water and an auger/step motor to dispense our gatorade powder. We plan to have a LCD interface in order for a person to input the amount of drink they desire. In our research we found explanations for linking solenoid valves and an auger to an Arduino so we now feel much more comfortable with the direction of project. Knowing are design has allowed us to have a better idea of the parts we will need and there prices. Therefore we updated our budget and have a good idea at what is necessary. We spent about 5 hours working together on Saturday. We both also did research outside of this time. We plan to ask for help this week on choosing our loading cell/scale given that we need process measurements in order to be successful. | ||
*update Gantt Chart (will post) <br /> | *update Gantt Chart (will post) <br /> | ||
*research with Jacob<br /> | *research with Jacob<br /> |
Revision as of 17:42, 1 October 2017
Week 2 (9/15/17)
- Had group issues
- met with jim
Week 3(9/22/17)
- Decided on project
- Met with Jim and Natalie
Week 4 (9/29/17)
This week we researched methods of implementing are idea as well as coming up with a first draft of our design. Our design uses a solenoid valve to dispense water and an auger/step motor to dispense our gatorade powder. We plan to have a LCD interface in order for a person to input the amount of drink they desire. In our research we found explanations for linking solenoid valves and an auger to an Arduino so we now feel much more comfortable with the direction of project. Knowing are design has allowed us to have a better idea of the parts we will need and there prices. Therefore we updated our budget and have a good idea at what is necessary. We spent about 5 hours working together on Saturday. We both also did research outside of this time. We plan to ask for help this week on choosing our loading cell/scale given that we need process measurements in order to be successful.
- update Gantt Chart (will post)
- research with Jacob
- finalize budget